Athletic Centre Competition Arena Returf

As part of Sydney Olympic Park Athletic Centre continued effort to improve and maintain world class facilities, the Athletic Centre is currently undergoing major turf works at the Competion Arena. 

Commencing from Monday 7 December, turf maintenance works will continue for several weeks, resulting in a superior quality surface.  Works covered within the project include the removal of existing turf, supply of new organic material, levelling, harrowing, laying and topdressing the field of play area. 

We look forward to reopening the area on Monday 15 February 2010. 

All general training activity will occur at the Warm Up Arena, check the General Training Calendar for training times.  Click here for General Training Calendar


Stage 1 - Monday 7 December 2009
  • Site Establishment
  • Track Protection

 

Stage 2 - Tuesday 8 December 2009

  • Excavation of existing turf surface

Stage 3 - Thursday 10 December 2009

  • Commence laser levelling

Stage 4 - Monday 14 December 2009

  • Lay of turf 


Stage 5 - Monday 21 December 2009

  • Completed lay of turf


 

     